In 2007, Jan De Nul Group and La Naval Shipyard in Bilbao signed a contract for the construction of a 30,500 m³ trailing suction hopper dredger, later named TSHD Charles Darwin. Vuyk Engineering Rotterdam was responsible for the main part of the basic design, working closely with Jan De Nul to meet the specific requirements of the vessel.

The dredger was designed with a limited draught and reduced vessel length, making it ideal for shallow or restricted environments. Vuyk prepared the main construction drawings for the hull and superstructures, including all foundations for the dredging equipment. A global FEM hull strength analysis was carried out to ensure compliance with all relevant rules and regulations. Arrangement drawings included the overall layout of the vessel, such as the engine room.

The design focused on efficient use of installed power, resulting in lower fuel consumption and reduced emissions. Two 1200 mm suction pipes with submerged dredge pumps of 3,400 kW each were installed. The vessel also features double-walled, electrically driven shore discharging dredge pumps with a total power of 15,000 kW, enabling high-rate discharge over long distances.

Scope of work TSHD Charles Darwin

  • Basic design of the vessel
  • Hull and superstructure construction drawings
  • FEM global hull strength analysis
  • Arrangement drawings

Photo credit: Jan De Nul

Related ship design projects: